Payment deadlines in construction run from specific events: the last day you furnished work, the completion of the project or a recorded notice. Miss one and the right can be lost. Below are Louisiana's key deadlines, with sample dates worked out from Dec. 1, 2026, around DOTD's upcoming letting dates. The dates are illustrations only. Count your own from your actual dates, and check the statute.
The deadlines
- File statement of claim or privilege (private work) (La. R.S. 9:4822): 60 days; if the triggering notice is filed on Dec. 1, 2026, by about Jan. 30, 2027.
- Residential claimant with notice of nonpayment (La. R.S. 9:4822): 70 days; if the triggering notice is filed on Dec. 1, 2026, by about Feb. 9, 2027.
- Public work: file and record sworn statement (La. R.S. 38:2242): 45 days; if acceptance is recorded on Dec. 1, 2026, by about Jan. 15, 2027.
The same deadlines from three start dates
- File statement of claim or privilege (private work): from Dec. 1, about Jan. 30, 2027; from Jan. 15, 2027, about March 16, 2027; from March 31, 2027, about May 30, 2027.
- Residential claimant with notice of nonpayment: from Dec. 1, about Feb. 9, 2027; from Jan. 15, 2027, about March 26, 2027; from March 31, 2027, about June 9, 2027.
- Public work: file and record sworn statement: from Dec. 1, about Jan. 15, 2027; from Jan. 15, 2027, about March 1, 2027; from March 31, 2027, about May 15, 2027.
Lien papers are filed with the parish recorder of mortgages. Calendar months and day counts can land on weekends or holidays, and some deadlines are measured from events you may not see, such as a recorded notice of completion or acceptance. Build in a margin.
Public jobs
Public property generally cannot be liened, so payment on public jobs is protected by bonds. Louisiana public works contracts over $25,000 per project require a payment bond of at least 50% of the contract price (La. R.S. 38:2241).
On a public job, ask the awarding agency early for a copy of the payment bond, and note the surety's name and address. Notices often must go to the surety or the bonded contractor, not just the party that hired you.
Federal-aid highway jobs
Most DOTD highway projects use state contracts with state payment bonds, even when federal money is involved. The federal Miller Act applies to contracts let by federal agencies themselves, not to state DOT lettings. Check the bond named in the contract.
Practical steps
- Log your first and last furnishing date for every job.
- Send any required preliminary notices as soon as you start.
- Ask the owner or agency about notices of completion, termination or acceptance.
- When a payment is late, count backward from the earliest deadline, not the latest.
Our lien and bond guide has the statute text and links.
Terms used in this story
- Change order: a written change to a signed contract's work, price or time.
- Notice to proceed: the agency's written go-ahead that starts the contract clock.
- Prevailing wage: minimum wage and fringe rates set for public works by trade and area, where state or federal law applies.
- Surety: the company that issues bid, performance and payment bonds and stands behind the contractor's obligations.
- Letting: the scheduled date when an agency opens and reads the bids for a group of projects.
- Proposal: the bid package for one project: the quantities, special provisions and forms a bidder fills in.
- Addendum: a change the agency issues to a proposal before the letting; bidders must acknowledge each one.
- Plan holders list: the list of firms that requested a project's plans, which subs and suppliers use to find primes to quote.
- Bid bond: a surety's guarantee, usually a percentage of the bid, that the low bidder will sign the contract and furnish the required bonds.
- Payment bond: a surety bond that guarantees the prime will pay its subs and suppliers on a public job, standing in for lien rights.